Greetings from our ongoing projects
Alholmens kraft
The Alholmens Kraft project is well underway and progressing on schedule.
Foundation, backfilling, and flooring works have largely been completed.
The steel frame, exterior wall panels, and load-bearing roof sheeting installation have progressed well.
Our focus is now on completing the frame, the waterproofing roof, and other supplementary works.
Last week, the electric boilers supplied by Parat Halvorsen AS from Norway were installed.
The project will then enter its final phase, with flooring installation and handover scheduled for early 2027.
Watch the installation video of the electric boilers
Vimpeli Sports hall
Vimpeli Sports Hall is currently on schedule, and construction works are progressing according to plan.
Structural framing, roofing, and concrete casting are the primary ongoing work phases. Design is largely complete, and ongoing works include ground floor structure work and the installation of EPS insulation.
Sandsund school

The Sandsund School project is progressing on schedule.
The exterior plastering works are complete, while partition wall works are ongoing.
Works in the connecting section as well as HVAC and electrical installations are ongoing.
Going forward, the focus is on interior construction works, drying, and the continued completion of technical installations.